At handover, a revised drawing is missing, an equipment manual is still in an email and the team has already moved to its next project. Preparing the DOE—dossier des ouvrages exécutés becomes a search for documents that should have been collected during the work.
This guide concerns construction projects in France. The DOE is the technical record of the completed works. Its required contents, delivery date and format depend on the contract. It helps the owner and operator understand and maintain what was built.
Key takeaways
- Define the expected handover documents at the start of the project.
- Keep as-built drawings, operating instructions, maintenance information and required checks current.
- The DOE and the DIUO serve related but distinct purposes.
- File documents as they are produced and name someone to review completeness.
What is the DOE used for?
The file records the building or works as delivered: actual layouts, installed products, equipment and maintenance instructions. It should help an operator locate services, identify a replacement component or prepare a later intervention without reconstructing the whole project history.
A folder full of documents is not necessarily a usable DOE. References, versions and a clear index matter as much as the number of files.
Which requirements apply in France?
For a contract referring to the 2021 CCAG Travaux, article 40 specifies the documents to supply when requesting acceptance, including as-built execution drawings, product information and operating and maintenance instructions. The contract's specific documents set the detailed contents and digital format. Missing documents may trigger the contractual penalties or withholding arrangements described in that framework. See article 40 on Légifrance.
For a private contract, check the signed documents and any standard they incorporate, including NF P 03-001 where referenced. Do not assume that every project uses the same list or timetable.
Check the contractual checklist
Agree the required items, delivery dates, recipients and file formats with the project team. A generic checklist does not establish that your contractual obligations are complete.
Organise the file into useful groups
1. Updated technical records
Keep drawings that reflect the executed work: relocated services, changed openings and substituted equipment. Include updated calculations or specifications when required.
2. Equipment information
Collect technical sheets, installed references, operating manuals, maintenance intervals and manufacturer warranty information. Confirm that the documents describe the equipment actually installed.
3. Checks and commissioning
File the test results, inspection records, commissioning documents and certificates requested for the work. Keep the record of any corrective action with the relevant observation.
4. Handover and project administration
Include the documents required by the project: acceptance records, outstanding items, completion evidence and useful contractor contacts. Keep personal data and access rights appropriate to the recipients.
5. Information for future interventions
The DIUO—dossier d'intervention ultérieure sur l'ouvrage supports risk prevention during later work. It is addressed by the French Labour Code, including article R4532-95. It is not simply another name for the DOE; coordinate the necessary contributions with the person responsible for that file.
6. Operational access and contacts
Record support contacts and the agreed handover procedure for connected equipment. Transfer credentials through an appropriate secure channel rather than placing reusable passwords in a widely shared document folder.
DOE, DIUO and as-built drawings
| Record | Main purpose |
|---|---|
| DOE | Document the delivered works for operation and maintenance |
| DIUO | Provide information useful for preventing risks during later interventions |
| As-built drawings | Show what was actually built; these can contribute to both files |
The project may organise these in related volumes, but each file still needs its own owner, purpose and required contents.
Who prepares the documents, and when?
Each contractor prepares the records for its scope of work, following the project's agreed coordination process. Identify who collects, reviews and delivers the combined file.
Start at mobilisation. When a product substitution is approved, a drawing changes or a test is completed, file the corresponding record. Waiting until handover makes missing documents harder to recover.
A practical collection method
- Define a project folder structure: drawings, equipment, checks and handover administration.
- Create a document register: expected item, owner, revision, due date and location.
- File records when produced: include the project reference and date.
- Review completeness regularly: chase specific missing items while the relevant team is still involved.
- Check the final package: open files, verify versions and confirm the recipient can use the agreed formats.
Krewsite documents, daily reports and report templates help organise records collected during work. They support preparation; a software folder alone does not certify a complete DOE.
For daily collection, see the site tracking guide and daily report template.
Frequently asked questions
Is the DOE compulsory?
Check the contractual framework and documents applicable to the project. A contract referring to the 2021 CCAG Travaux includes the requirements described in article 40. Private contracts need their own review.
When should it be delivered?
Use the contract's timetable. Under the cited CCAG framework, documents are supplied when requesting acceptance, with provisions for individual work packages. Prepare them early enough for review.
Can it be digital?
Yes. Agree the required formats, naming, access and delivery method. A file that cannot be opened by its intended recipient is not a useful handover record.
Who checks completeness?
Name the contributors and reviewer in the project organisation. Each contractor remains responsible for preparing the documents required for its scope; coordination should make gaps visible before handover.
Download a working document register
Download the site document checklist (CSV). Record each document's version, date, owner and location. Adapt it to your project requirements; it is a working register, not a complete DOE in itself.
Explore Krewsite document management or the 15-day trial. The web application is available in French and English.
This guide explains a French construction workflow. Refer to the applicable contract and official texts when determining the requirements for a particular project.