The installation team arrives on Monday morning. A room described as ready is still being used for storage, the printed drawing has changed, and the previous team leader is now on another site. Work starts with a series of phone calls.
A handover between site teams prepares the next job using information available when the previous team leaves. It applies both to a change of team leader and to one trade handing over to another.
The template below is an internal coordination aid. Use it alongside the documents and discussions required for your project.
Key takeaways
- Describe each zone's condition using observable facts.
- State what must be in place before the next team starts.
- Link decisions to current drawings and documents.
- Ask the incoming team to confirm they have read the brief and address open points.
When should you prepare the handover?
Arrange a discussion before the team familiar with the completed work leaves. The time needed depends on outstanding points. A brief and a few photos may be enough for a short job. Several zones or technical interfaces may require a joint site visit.
Include this meeting in the construction schedule. If it happens after the next team is mobilised, blockers will be discovered just as work should begin.
The handover organiser should also check who can authorise changes. The incoming team needs to know where to raise a difference between the drawing and actual site conditions.
Describe what is actually ready
“Plumbing 90% complete” tells a dryliner little about whether a particular zone can be closed. Describe the work and its limits:
Unit 12: bathroom pipework installed. Inspection planned for Tuesday morning. Keep the entrance-side partition open until the package manager confirms. The unit's other zones still need review before closing.
This separates completed work from work the next team can start and retains an explicit inspection point.
Give each zone a clear status: ready for the planned work, check together, or blocked, with the condition to resolve. Adapt the terms to your organisation and avoid colours that people interpret differently.
What to tell the next team leader
Applicable drawings and decisions
State the drawing reference, revision or version date, and where to find it. Mark decisions still awaiting approval as pending.
A photo of an annotation sent in a conversation must be linked to the relevant document. The next team should be able to tell whether it is a proposal, an approved instruction or an old discussion.
Access and working constraints
Specify accessible zones, agreed working hours, opening arrangements and known constraints. Identify storage areas and routes that must remain clear.
Pass on applicable safety instructions and relevant contacts too. The brief helps people find this information; it does not replace the prevention procedures required for the work.
Equipment and materials
A planned delivery may still need confirmation. Distinguish materials already on site, those ordered and those whose availability remains uncertain.
For shared equipment, state its location and expected release date. If a machine is moving to another project, name the person arranging the transfer.
Team handover brief template
Copy this structure into your report or internal document.
| Section | Details to record |
|---|---|
| Project and zone | Reference, building, level and room |
| Outgoing team | Lead and work contact details |
| Incoming team | Lead and planned start date |
| Completed work | Work carried out and precise limits |
| Zone status | Ready, needs checking or blocked for the planned work |
| Open point | Observed fact, consequence and required action |
| Action owner | A named person for each point |
| Deadline | Date needed to keep the planned start |
| Documents | References and access to applicable versions |
| Photos | Zone overview and useful details |
| Access and equipment | Entry arrangements, storage and available equipment |
| Incoming team's response | Questions, differences found and acknowledgement |
On a small project, put shared information at the top, then keep one row per open point. This lets you track matters progressing at different speeds separately.
A renovation handover example
In this fictional example, a painting team is due to follow surface preparation work.
The brief states: “Bedroom 1 ready for the start-up inspection; bedroom 2 awaiting a repair to the window reveal; living room occupied by carpentry materials.” Each point has an owner and agreed deadline.
The incoming team leader can plan by zone and ask for confirmation that the living room is clear before moving equipment. The construction manager can see which decision affects the schedule.
The zone details give the team more to work with than a general “preparation complete” status.
Check the handover when work starts
Ask the incoming team to compare the brief with site conditions. Record differences before changing the programme. Retain the original brief's date and add the response so the development of each point remains visible.
Observations can then feed the daily report. Krewsite links reports to their project and keeps them in the history, providing context for team changes.
Try the brief at the next team change. After the first morning, ask the incoming leader which information was missing and adjust the sections accordingly.