By Krewsite5 min

Compare planned and actual hours by task, estimate the remaining work and investigate variances with a worked construction example.

A project can meet its completion date while using more labour hours than planned. If the owner discovers the difference at closeout, the lesson can inform future quotes, but decisions on the current project come too late.

Tracking planned and actual hours compares the labour budget with physical progress. It needs a consistent scope and an estimate of work still to be completed.

Key takeaways

  • Break the budget into tasks field teams can identify.
  • Compare hours used with observed progress.
  • Re-estimate the hours needed to finish each task.
  • Record the causes of variances before changing the schedule or estimate.

Choose a breakdown the team can record

Start with a few items reflecting real project stages, such as preparation, removal, installation and finishes. People should be able to allocate a day or half-day without constant uncertainty.

A project total shows overall hours. Task-level figures help explain a variance. Too many sub-items can make entries difficult and encourage approximate allocation.

Agree at the start how to record travel, materials handling, remedial work and waiting. Use the same conventions in the budget and actual records.

Measure progress with a concrete unit

Elapsed time does not measure completed work. Using one week of a two-week programme does not mean half the work is finished.

Where possible, use a physical unit: square metres fitted, completed units, installed equipment or finished zones. Check that the units are comparable. A room requiring many cuts may take more work than a large clear area.

For tasks that are hard to quantify, agree observable milestones with the team leader. The daily report can retain the context: blocked access, a substrate needing repair, pending approval or a scope change.

Example: 80 hours used against a 120-hour budget

These figures are a fictional calculation example, not productivity rates to apply to your quotes.

A business budgets 120 hours to install 200 m² of broadly comparable work. At the weekly review, 100 m² are complete and 80 hours have been used.

MeasureCalculationResult
Physical progress100 / 20050%
Labour budget used80 / 120About 67%
Budgeted hours for completed quantity120 × 50%60 h
Variance on completed quantity80 − 60+20 h

The team has used 20 hours more than the budget for the completed quantity, assuming effort is proportional to area.

Investigate the difference. Preparation concentrated at the beginning may explain part of it. Remaining zones may be simpler. Projecting only the observed rate gives 160 hours in total, but assumes the same conditions continue.

Estimate hours at completion

Ask the field manager to estimate the time needed to finish the remaining tasks:

Estimated hours at completion = actual hours to date + estimated hours to finish.

In this example, if the team leader estimates 65 hours remaining, the forecast is 145 hours. The projected variance against the original budget is 25 hours.

Record what supports the 65-hour estimate: remaining areas, known repairs, access conditions and planned staffing. At the next review, this explanation helps show why the estimate changed.

Retain the original budget as a reference. If scope changes, track the adjustment separately so you can compare like for like.

Find the cause before deciding

An overrun can come from the estimate, site conditions or remedial work. A time entry assigned to the wrong site can also distort the comparison.

Possible causeEvidence to checkPossible decision
Different quantityCompleted quantities and original scopeRecalculate remaining work from observed quantities
Different substrate or accessPhotos and field observationsAdjust preparation and sequencing
WaitingDate, duration and reason for the blockageClarify prerequisites for the next job
Remedial workWork repaired and confirmed reasonArrange checks before the next stage
Incorrect allocationTime record and relevant projectCorrect through the internal approval process

Adding a person helps only if zones, equipment and materials allow parallel work. Check those conditions before increasing staffing.

A table for your weekly review

Use one row per task with these columns:

  • Original hours budget and corresponding scope.
  • Planned quantity and quantity actually complete.
  • Cumulative actual hours, after checking allocations.
  • Estimated hours to finish, with revision date.
  • Forecast at completion and variance against budget.
  • Documented cause, agreed action and owner.

Add a short note when an assumption remains unconfirmed. Identifying uncertainty helps prepare an on-site check.

Connect time tracking with project management

Hours alone cannot calculate a project's full margin. Materials, subcontracting, equipment and other project costs also matter under your management method.

Start by making hour allocations and progress updates reliable. Krewsite time tracking and reports form part of the project record. Use them in the weekly review, then compare them with your labour budget.

Our project tracking guide explains how this fits into daily management. On your next project, begin with one significant work item to test the breakdown and recording conventions before extending the table to the whole job.