“Could you move that socket as well?” The team is on site, materials are available and the client wants to move forward. Yet the change may require labour, supplies and a programme adjustment that were not included in the original quotation.
To manage additional works on site, connect five things: the request, the agreed scope, the estimate, the approval and the work completed. This method helps the site team, office and client keep track of them.
Key takeaways
- Check what the accepted quotation already includes.
- Describe the request and its consequences before scheduling the addition.
- Obtain documented approval from the authorised person.
- Keep the order, progress record and completion evidence together.
1. Check the agreed scope
Before treating an intervention as additional work, read the relevant contract documents: the accepted quotation, specification, drawings and changes already approved. A request may be an addition, a clarification or something already included.
Describe the difference in concrete terms:
The quotation includes two sockets on the north wall. The request is to add a third socket on the opposite wall.
This gives everyone a shared starting point. If the scope remains unclear, have it reviewed before promising a price or completion date.
2. Record the request when it arrives
A request made during a visit must be available to the person preparing the estimate. Record the project, zone, date, requester and proposed change. Attach useful photos or references and assign someone to follow up.
“Kitchen change” leaves room for interpretation. “Add a socket above the worktop, on the window side; position to be confirmed” identifies what still needs a decision.
At this stage, distinguish request received from work authorised. Use a consistent site photo organisation method so supporting images remain understandable.
3. Estimate the work and its effect on the programme
A change may involve materials, labour, travel, equipment hire and another trade. Check its effect on the sequence of work: an extra delivery, a finish that needs reworking or a new team availability requirement.
Illustrative example: three hours at an estimated internal cost of €35 per hour, plus €85 of materials, gives an estimated direct cost of €190 before other overheads and margin.
This calculation does not determine the selling price. It shows why even a small request needs an assessment. Compare your assumptions with planned and actual site hours.
4. Document approval before scheduling the addition
For a change to the quotation, prepare a document describing the work, its price and any effect on timescales. Have it approved by the authorised person.
In the French context, the FFB stresses the importance of being able to prove that additional works were ordered and recommends keeping written evidence. Requirements vary with the contract and circumstances. FFB guidance on evidence for additional works
Obat describes a quotation amendment as a document linked to the original quotation that sets out the accepted changes. Obat’s guide to quotation amendments
Use explicit internal statuses: to estimate, awaiting approval, approved and declined. The team needs to know which interventions can be scheduled. This organisational method supports the contract process; it does not resolve a contractual dispute.
5. Link completion to the approved request
Once the work is authorised, retain the reference to the accepted document in the project record. After completion, add the date, work carried out, photos and any outstanding points.
The office then has a history to prepare invoicing and answer client questions. A daily site report can document execution; keep the document establishing the order and its conditions as well.
A simple request tracking sheet
Adapt this internal template to your organisation. It does not replace a contractual amendment.
| Field | Information to record |
|---|---|
| Reference | AW-001 |
| Project and zone | Name, building, room |
| Requester and date | Who requested the change and when |
| Change | Precise description |
| Original quotation | Reference and affected item |
| Estimate | Associated document |
| Timescale | Known effect or confirmation needed |
| Approval | Status and approval reference |
| Completion | Owner, date and evidence |
How should you respond to the client?
You can use straightforward wording:
I’ve recorded your request. We’ll check what it changes against the quotation and send you the price and any effect on the programme before scheduling the work.
The client knows what happens next. The site team can pass the request to the office, and everyone has an identifiable next step.
Frequently asked questions
Is a WhatsApp request enough?
Keep the exchange, but check that it identifies the work, accepted conditions and person approving it. The legal effect of a message depends on the circumstances and contract.
Should small additions be tracked?
The same template can cover modest requests and major changes. It helps with estimating and preserves their history.
What if the work has already been completed?
Gather the existing request, exchanges, quotation, photos and work records. Present the situation to the client without fabricating or backdating approval. If there is a disagreement, have the file reviewed against the relevant contract.
Sources reviewed for the original article on 6 November 2026.